What will be the cost of block wall masonry?/Rate analysis of concrete block masonry.

 Let us consider solid concrete block masonry as shown in the drawing for calculation purposes.



Given data:

Length of the block masonry = 16ft.

Height of the block masonry = 10ft.

The thickness of the block masonry = 0.5ft.


Calculation:

The total volume of the block masonry

= [length × height × thickness]

= [16ft. × 10ft. × 0.5ft.]

= 80 cu ft.


The total area of block masonry

= [length × height] 

=[16ft. × 10ft.] 

= 160 sq ft.


A. Material calculation:

Read the article "Calculating the quantity of materials in a 100 cubic ft. block wall." before proceeding further.

       No. of blocks required/100 cu ft. of wall = 210 nos.

      No. of Cement bags required/100 cu ft of wall = 1.038 bags

      The volume of sand required/100 cu ft. of wall = 7.634 cu ft.

Note: The quantity of blocks, cement & sand/ 100 cu ft. is taken from the above-mentioned article.

1. No. of  concrete blocks required 

      = [(vol. of block wall ÷ 100 cu ft.) × blocks/100 cu ft.]

      =  [(80 cu ft. ÷ 100 cu ft.) × 210 nos.]

     = 168 nos.


2. No. of  cement bags required 

      = [(vol. of block wall ÷ 100 cu ft.) × bags/100 cu ft.]

      =  [(80 cu ft. ÷ 100 cu ft.) × 1.038 bags]

     = 0.83 bags.


3. The volume of sand required 

=  [(vol. of block wall ÷ 100 cu ft.) × sand/100 cu ft.]

  =  [(80 cu ft. ÷ 100 cu ft.) × 7.634 cu ft.]

6.11 cu ft.


B.  Labor calculation:

The labor rate per sq ft. of the block masonry ranges from INR 10/- to 15/- depending upon the region.

Let us consider an average rate of INR 12/- per sq ft.


The total cost of labor for block masonry

   = total area of block masonry in sq ft.  × labor rate/ sq ft.

   = 160 sq ft. × 12/-

   = INR 1920/-


Go through the article👇

👀. What will be the cost of 9" brick wall masonry?/ Rate analysis of 9"  thick brick wall work.


Now, let us calculate the total cost of block masonry in table format.

Sl. no.

Item.

Qty.

Rate.

in INR.

Unit.

Cost

in INR.

1.

Solid block

168

28/-

Nos.

  4704.00

2.

Cement

0.83

400/-

bag

    332.00

3.

Sand

6.11

60/-

Cu ft

    366.60

4.

Curing

Lump-sum

    200.00

5.

Miscellaneous

Lump-sum

    150.00

6.

                                                      The material cost =

 5752.60

7.

                                                       Add 5% wastage =

   287.63

8.

                                                   Total material cost =

 6040.23

9.

                                                                Labour cost =

 1920.00

10.

                       The total cost of block masonry =

7960.23

 

Note: To get accurate results, insert your regional market rate of materials & labor, in the above table.

The cost of block masonry/sq ft.

= [total block masonry cost ÷ total block wall area]

= 7960.23 ÷ 160

= INR 49.75/sq ft.

The cost of block masonry/ cu ft.

= [total block masonry cost ÷ total block wall volume]

= 7960.23 ÷ 80

= INR 99.50/cu ft.


To go through rate analysis & cost-related articles, click here.


Thank you for going through this article. Have a good day😄.

If you have any queries, you can ask me in the comment box👇.




Share:

1 comment:

  1. Impressive breakdown! You've clearly outlined the calculations for estimating the block wall masonry. Your approach in calculating the total volume and area is spot-on. To enhance the analysis, including the unit costs for concrete blocks and labor would provide a comprehensive cost estimate. Keep up the good work!

    Visit Here!

    ReplyDelete

Translate

Blog Archive

popular posts

Recent Posts

Google search