Let us consider a single brick wall of size 10ft × 30ft.× 0.333 ft. (4")  as shown in the drawing.





Now, we will build this wall with a conventional brick of size 9 inches × 4 inches × 3 inches as shown in the image below.

Given data:

Length of the brick wall = 30 ft.

Height of the brick wall = 10 ft.

The thickness of the brick wall = 0.333 ft.

Brick size = 9 inches × 4 inches × 3 inches

Mortar thickness = 10mm = 0.39 inches



To calculate the number of bricks required to build this wall, first, we will find out the volume of the wall and the volume of a single brick with or without mortar.

The volume of the brick wall 

                  = Length × Height × Thickness 

                  = 10ft × 30ft × 0.333 ft.

                  = 100cu ft.

Now, the volume of the brick

                 = l × h × t

                 = 9 inches × 3 inches × 4 inches 

                    ( By converting them into ft.)

                 = 0.75ft × 0.25 ft × 0.333 ft.
 
                 =0.0625 cu ft.


From the drawing given below, you can observe that the addition of the mortar thickness comes on the 2 sides of every brick.


So, the volume of the brick with mortar

                     = 9.39 inches  ×3.39 inches  × 4 inches

                     =127.3284 cubic inch.

                     =0.0737cu ft.

 

1.  The number of bricks required

                  = volume of the wall ÷ volume of the brick with mortar

                  = 100 cu ft. ÷ 0.0737 cu ft.

                  =1357 nos.


The volume of mortar required 

        = volume of the brick wall - the volume of the total no. of bricks 

        = 100 cu.ft. - (1357 nos. × 0.0625 cu.ft.)

        =   100 cu ft. - 84.812 cu ft.

           =15.187 cu ft.


Let us prepare this 15.187 cu ft. of mortar in a 1: 6 ratio to build this 100 cu ft. of the brick wall.

Dry volume of the cement mortar

           = 1.33 × wet volume of the mortar.

          = 1.33 × 15.187

           = 20.198 cu ft.


   2.  Volume of the sand

          = (6  ÷ ( 6 + 1)) × 20.198

           = 0.8571 × 20.198

            = 17.312 cu ft. 


3. Volume of the cement 

   = total dry mortar vol. - volume of sand

    = 20.198 cu ft - 17.312 cu ft.

    =2.886 cu ft.

As you know, one bag of cement = 1.226 cu ft.

  Number of cement bags 

    = 2.886 cu ft. ÷ 1.226 cu ft.

    =   2.354bags.


Let us now find out the materials required for 1 cu ft. & 1 CUM. of  4" brick wall.

1. Bricks:

Bricks required for 1 cu ft. of brick wall

= 1357 nos. ÷ 100 

= 13.57 nos.


Bricks required for 1 CUM of brick wall

= 13.57nos. × 35.315

= 479 nos.


2. Cement:

Cement required for 1 cu ft. of brick wall

= 2.354 bags. ÷ 100

= 0.0235 bags.

Cement required for 1 CUM of brick wall

= 0.0235 bags × 35.315

= 0.83 bags.


3. Sand:

Sand required for 1 cu ft. of brick wall

= 17.312 cu ft. ÷ 100

= 0.1731 cu ft.


Sand required for 1 CUM of brick wall

= 0.1731 cu ft. × 35.315

= 6.11 cu ft.

     Continued 👉   What will be the cost of single (4") brick wall masonry?/ Rate analysis of 4" brick wall.


Share:

1 comment:

  1. Moos & Unkraut professionell entfernen lassen Wow, cool post. I'd like to write like this too - taking time and real hard work to make a great article... but I put things off too much and never seem to get started. Thanks though.

    ReplyDelete

Please do not enter any spam link in the comment box

Translate

Blog Archive

popular posts

Google search

Recent Posts

Pages